When to reorder clothing stock so you do not sell out
By Splot · · 3 min read
A T-shirt that sells 8 a week and takes 10 weeks to remake has to be reordered while 80 are still in stock, so a first run of 50 sells out about six weeks before its reorder arrives.
On this page
When should you place a reorder?
When the stock left equals what will sell while the reorder is being made. Multiply the pieces sold in a week by the weeks the reorder takes, and that is the stock level at which the order has to go in.
In the working example a tee sells 8 a week and the reorder takes 10 weeks, so the order has to be placed while 80 tees are still on the shelf. A first run of 50 never has 80 on the shelf. That is the ordinary position for a new brand, and the rest of this guide is about what to do with it.
How long does a reorder take?
Shorter than the first order, because the pattern exists and the sample is approved. What remains is the fabric, the production and the freight.
| stage | weeks |
|---|---|
| Fabric | 3 to 4 |
| Production | 4 to 6 |
| Freight | 1 to 4 |
| Total | 8 to 14 |
Ten weeks is a fair planning number for a factory in Europe. The clock starts when the deposit is paid and the fabric is booked, and a reorder that waits a week for a decision arrives a week later.
Why does a first run sell out before the reorder lands?
Because nobody knows the weekly sales until the first weeks have passed. At 8 a week, 50 tees last a little over six weeks.
Say the brand watches two weeks of sales and then reorders. By then 16 tees have gone and 34 are left, which is just over four weeks of stock against a ten-week wait.
| week | what happens | tees in stock |
|---|---|---|
| 0 | Launch | 50 |
| 2 | Reorder placed | 34 |
| 6 | Sold out | 0 |
| 12 | Reorder arrives | 50 |
The shop is empty for about six weeks. The cost of that is the sales not made: 6 weeks at 8 a week is 48 tees, nearly a whole run.
How can the gap be shortened?
There are three ways, and they can be combined.
- Book the fabric for two runs at the first order. The fabric is three or four of the ten weeks. If the mill or the factory holds enough for a second run, the reorder is production and freight only, about seven weeks. Ask what holding it costs and how long they will keep it.
- Decide sooner. Two weeks of sales is enough to see whether 50 pieces will last. Reordering in week one instead of week four is worth three weeks of stock.
- Take pre-orders for the restock. A sold-out page that takes orders for a stated date keeps most of the sales the gap would lose, and it shows which sizes to make. How to run a pre-order for a first clothing run covers the mechanics.
With the fabric held, a reorder placed in week 2 arrives in week 9, and the gap falls from six weeks to about three.
Should the reorder repeat the first run?
Same garment, different size split. The first run was divided on a guess, and by week two the sales say which sizes were short.
Run the same sum for each size. If M sells 3 a week and 9 are left, M has three weeks of stock, whatever the total says. Sizes sell out one at a time, and a tee that is in stock only in XS and XL has stopped selling well before the count reaches zero. How to split sizes on a first clothing order shows how to keep any size from falling too low.
Keep everything else identical: the same fabric from the same mill, the same factory and the same approved sample as the reference. A reorder with a small improvement in it is a new product and needs its own sample.
What does the reorder cost, and when is it paid?
Less than the first run, because the pattern, the samples and the photos are already paid for. In the example a second run of 50 costs €800: €650 of garments, €100 of labels and packaging and €50 of delivery.
The timing is the hard part. A common structure is 30% when the order is placed and the balance before it ships, and the example uses it; Splot's own terms are 60% before production and 40% before dispatch. Placed in week 2, the deposit is due when only 16 tees have sold, so the reorder is funded partly from the first run's sales and partly from the brand's own money.
Planning the reorder before the first run is placed
- Ask the factory how many weeks a repeat order takes, with and without fabric in stock.
- Ask what it costs to hold fabric for a second run.
- Decide at launch which week you will look at the sales and choose.
- Count stock per size, in weeks, and not as one total.
- Keep the deposit for the reorder out of the launch budget.
For how the reorder changes the profit of the whole launch, see how many pieces a first clothing run has to sell to break even.