A week-by-week launch plan for a first clothing drop, from sample to sell-out

By Splot · · 4 min read

A first drop runs about 20 weeks from ordering the sample to delivery, and for a run of 75 T-shirts the plan turns on three numbers: about 300 people on the list before the pre-order opens, at least 25 orders when it closes, and the last 15 or so pieces sold to the list after delivery.

On this page
  1. How long does a first clothing drop take from sample to sell-out?
  2. What happens in each week?
  3. Which numbers decide whether the drop goes ahead?
  4. What has to be ready before the pre-order opens?
  5. How do you sell the last pieces?

How long does a first clothing drop take from sample to sell-out?

About 20 weeks to delivery, then as long as the last pieces take to sell. The weeks are set by production. Under Splot's terms a sample takes three to six weeks, and production takes six to ten weeks once the sample is approved. A two-week pre-order sits between the two, and the photos and the product page need about two weeks before it opens.

The plan below assumes the slow end of each range, a T-shirt sold at €45, and a target of 60 pre-orders against a run of 75, the example in how to run a pre-order. Where the sample comes back sooner, every later week moves up.

What happens in each week?

Four things run at once: the garment, the shop, Instagram and the email list. Each row is the work for that stretch of weeks.

weekgarmentshopInstagramemail list
0Send the tech pack, order the sampleSign-up page liveFirst post: what you are making and whyWelcome email set up
1 to 5Sample made; fit session when it arrivesThree posts a week from the sample stageWelcome email to each sign-up; one update every two weeks
6Sample approved; price at 25, 50 and 100 piecesSize chart from the approved sampleThe approved sample"The pre-order opens on [date]"
7Photos of the approved sampleProduct page built; test order placed and refundedProduct photos; countdown sticker in StoriesReminder a week ahead
8Pre-order opens to the list for 48 hoursCountdown ends; pre-order post"It's open", with the number of pieces
8 to 9Pre-order open to everyoneFit and detail posts; first buyers' commentsOne reminder, and a last-day email
10Pre-order closes; run ordered, deposit paidPage switched to "sold out" or to a waiting listThe final countOrder confirmation and expected date
11 to 19ProductionFactory photos, cut panels, boxesAn update to buyers every two weeks
19Pieces measured before the run shipsShipping set upPacking tableDelivery date confirmed
20DeliveryPre-orders shipped within a weekBuyers' photos in Stories"It's shipped"; ask for a photo
21 onRemaining pieces on saleWhat sold first, what comes nextThe remaining sizes to the list first

The detail for each column is in its own guide: the website and the pages it needs, what to post on Instagram, the email list and what to send and the pre-order.

Which numbers decide whether the drop goes ahead?

Three, each checked on a set day so a shortfall is caught while there is still time to act.

checkdaytarget for 60 ordersif it falls short
People on the listweek 6, before announcing the dateabout 300Move the pre-order back two weeks and keep posting from the sample
Orders half-way through the pre-orderweek 9about 30, half the target (a working assumption)Send the reminder with fit photos and answers to the questions buyers asked; keep the closing date
Orders when the pre-order closesweek 10at least 25, the minimum runBelow 25: refund everyone, or pay for the difference and sell those pieces later

The list target comes from the conversion rate. If one in five people on the list buys, 60 orders need 300 people. The one in five is an assumption, and the drop is how you find your own rate. How a new clothing brand finds its first customers sets out where those people come from.

The 25 is Splot's minimum per style. Decide before the pre-order opens which way you will go if it closes below that, and say on the product page that orders are refunded if the run does not go ahead.

What has to be ready before the pre-order opens?

Check each line in week 7, the week before it opens:

  1. The approved sample has been photographed, in the production fabric and colour.
  2. The factory has confirmed the price at the quantity you expect and at the minimum.
  3. The factory has agreed a delivery date, and the product page states a later one.
  4. The product page has flat measurements for every size, the fibre composition, the price with VAT and the delivery cost.
  5. The withdrawal, contact and privacy pages are live.
  6. A test order has gone through on a phone and been refunded.
  7. The emails for "opens on", "it's open", the reminder and the last day are written and scheduled.

The money side of this list, what is paid before the first order and what the 60 orders leave, is worked out in the pre-order guide.

How do you sell the last pieces?

To the people who missed the pre-order, starting with the list. A run of 75 against 60 orders leaves 15 pieces, some of which go to exchanges. The rest are the easiest sales the brand will make, because the people on the list have watched the garment being made for 20 weeks.

  1. In week 20, email the list the sizes that are left before posting them anywhere else.
  2. Post buyers' photos in Stories through weeks 20 to 22, with the sizes left.
  3. Note which sizes sold out first and how many people asked for them.

If all 75 are gone by week 22, that is the signal to reorder. A reorder of the same garment skips the sample and the photos, which is why the reorder is where the money is. When to reorder covers the timing, and limited drops or always in stock covers how to say how many pieces there are.

Short answers

Can a first drop launch faster than 20 weeks?

Yes, by up to seven weeks. If the sample is right first time and the fabric is in stock, the sample takes three weeks and production six, which brings delivery to about week 13.

Should the pre-order open before the sample is approved?

No. Customers buy from the photos, so the photos have to show the garment the factory will make.

How many emails does a launch need?

Five to the whole list around the pre-order: the date, a week to go, the opening, a reminder and the last day. Buyers then get the order confirmation, a production update every two weeks and the shipping notice.